The New Sacramento Courthouse exterior skin has been substaintially completed - well done team! Enclos has completed curtainwall installation (except for leaveouts) and Clark Pacific has completed precast panel installation.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

April 22, 2022

The New Sacramento Courthouse structure has topped out - well done team! The new Sacramento Courthouse is the 10th tallest structure in Sacramento.

 

 

 

 

 

 

 

 

March 7, 2022

The New Sacramento Courthouse concrete has topped out - well done Urata & Sons Concrete LLC, McClone Construction and Pacific Steel Group. The core climbing forms have been removed.

 

January 20, 2022

The New Sacramento Courthouse interior build-out begins.

July 26, 2021

The New Sacramento Courthouse has started steel erection - True North Steel and O'brien Steel Erectors are erecting the steel structure.

July 13, 2021

The New Sacramento Courthouse has its first slab-on-grade section done - first slab concrete pour complete!

June 25, 2021

The New Sacramento Courthouse has its first core wall section done - first core wall concrete pour complete!

June 7, 2021

OC Jones & Sons Inc., Urata & Sons Concrete LLC and Drill-Tech Shoring & Drilling Inc. officially bottomed out the New Sacramento Courthouse - deep foundations and underground structure have been completed.

November 16, 2020

Construction of the New Sacramento Courthouse has officially started!

November 12, 2020

Clark Construction's contract for construction of the New Sacramento Courthouse has been approved. Official Notice-To-Proceed (NTP) has been received and construction will start Monday, the 16th of November.

August 28, 2020

Clark Construction has submitted the construction GMP for approval.

June 22, 2020

Clark Construction has officially launched the bid package request for proposal process. The pre-qualified bidders for all scopes (or bid packages) have been issued a Request for Proposal (RFP). RFP due dates are 7/15, 7/21, 7/23, and 7/28 (dependent on the bid package instructions). For further details or any questions, please use our contact page to connect with us directly.

May 8, 2020

Clark Construction published a public advertisement about the RFQ and the upcoming bidding process on the New Sacramento Courthouse in the Sacramento Bee newspaper. The advertisement will be in the Sacramento Bee on 05/08/2020 and 05/15/2020.

April 22, 2020

The State of California's Department of General Services (DGS) Office of Small Business and Disabled Veteran Business Enterprise Services sent out an announcement to all State-registered small businesses and Disabled Veteran Business Enterprises about the New Sacramento Courthouse and associated business opportunities.

April 8, 2020

Clark Construction provided update to subcontractor market regarding updated project timeline.

February 13, 2020

The Sacramento Regional Builders Exchange (SRBX) featured Clark Construction and the upcoming Sacramento Courthouse project in the first 2020 Quarterly Connect meeting held at the SRBX office in Sacramento. Our team provided the construction community an overview of the project and the associated business opportunities. The presentation can be found below.

Presentation

January 16, 2020

Clark Construction provided update to subcontractor market regarding updated project timeline.

October 16, 2019

Clark Construction was featured in the 2019 annual ASA (Associated Subcontractors Alliance) of Sacramento General Contractor Expo. Our team provided the construction community an overview of the project and the associated project business opportunities for local subcontractors to get involved in.


September 27, 2019

Clark Construction and the JCC hosted an industry outreach kickoff meeting with the construction community to provide an overview of the project and the associated business opportunities. The presentation can be found below.

Presentation

circle logo-modified.png
bottom of page